Q-2, r. 35.3.1 - Regulation respecting afforestation and reforestation projects eligible for the issuance of offset credits on privately-owned land

Full text
104. The promoter must notify the Minister when a project is terminated, within 45 days of the termination. The promoter must then submit a notice to the Minister including the information prescribed for the notice of termination provided for in section 10 and updating the information contained in the project notice provided for in section 78 and the summary of the aggregation provided for in section 101.
The promoter must include a report on the state of forest stands drawn up by a member of the Ordre des ingénieurs forestiers du Québec when the project has not been verified to ensure the compliance of the measures taken by the promoter in accordance with Schedule G during the last request for the issuance of offset credits.
M.O. 2022-11-17, s. 104.
In force: 2022-12-29
104. The promoter must notify the Minister when a project is terminated, within 45 days of the termination. The promoter must then submit a notice to the Minister including the information prescribed for the notice of termination provided for in section 10 and updating the information contained in the project notice provided for in section 78 and the summary of the aggregation provided for in section 101.
The promoter must include a report on the state of forest stands drawn up by a member of the Ordre des ingénieurs forestiers du Québec when the project has not been verified to ensure the compliance of the measures taken by the promoter in accordance with Schedule G during the last request for the issuance of offset credits.
M.O. 2022-11-17, s. 104.